Total Build were asked by Suffolk Wildlife Trust to construct a new agricultural building at their Carlton Marshes Nature Reserve Site. The project was completed on time and within budget to the delight of the client.
Total Build were approached to tender for a new agricultural building to be erected at Carlton Marshes Nature Reserve in Carlton Colville, Suffolk. A steel framed building with low level block work was required. The structure was to then be clad with wood to and concrete corrugated roof sheets with skylights installed.
Having won the tender, foundations were dug and poured after which bolts for the steel uprights were sunk within the required areas. Drainage for stormwater was provided and a soak-away was installed. Services for fresh water and electricity were then brought up to the site.

A sub contractor installed the steel uprights for the buildings frame. As all bolts were already installed within the foundations by Total Build the process of placing and securing the uprights was quick and painless.
A single course of blocks was then laid around the building which was used as a level by which the internal floor was screed with concrete. The floor was poured in the warm summer months so a retarding agent was sprayed over and covered with polythene so it didn’t set too quickly and crack.

Once the floor was finished another three courses of block-work were laid to the required height. The steel sub-contractors then returned to install the steel roof frame, double doors and concrete corrugated roof sheets with skylights.
Castle style treated softwood cladding was then fitted to the exterior of the building and the steel frame doors. Low level sockets and lighting were then installed which completed the construction of the building. Finally, Vmex perimeter fencing was installed around the site which created a secure compound.
Every project at Total Build regardless of size or complexity receives the same care and obsessive attention to detail as if it were our own.
22 September 2023
Castle Point Development at Burgh Castle, Great Yarmouth.3 February 2022
Total Build Completes Luxurious Development at Strumpshaw.Haversham House, Dickens Court, Blundeston, Lowestoft NR32 5BA.
Copyright 2026 Total Homes - All Rights Reserved. Web Design by Bluedepth Creative